Description: This Project consists of:
1. 276LF of 6” water line by open cut.
2. 4975 LF of 8” water line by open cut.
3. 15 LF of 10” water line by open cut.
4. 4975 LF of 12” water line by open cut.
5. 3795 LF of 16” water line by open cut.
6. 140 LF of 8” water line by Uncased bore.
7. 440 LF of 12” water line by Uncased bore.
8. 140 LF of 8” water line by Cased Bore.
9. 20 LF of 12” water line by Cased bore.
10. 130 LF of 16” water line by Cased bore.
11. 978 LF of 8” water line by pipe bursting.
12. Temporary water line and service connections.
13. Asphalt and concrete pavement repair.
14. Traditional mill & overlay operations
The estimated Project completion date is September 2025.
The engineer’s opinion of probable construction cost is $10,150,000.
Location: Tarrant County, TX