Fort Laramie Canal Tunnel 1&2 Rehabilitation

Fort Laramie Canal Tunnel 1&2 Rehabilitation

Location: New York

Posted Date: December 8, 2023

Expiration Date: January 18, 2024

State: NE

Description: Construction of the Fort Laramie Canal Tunnel 1 & 2, including the four portals to convey a design discharge of 1,532-cfs, with free-board of irrigation water annually between May through September. Preconstruction services, including but not limited to value engineering constructability, risk review, cost modeling, and scheduling from a qualified CMAR. During the preconstruction process the CMAR will have the ability to bid self-performance work authorizations for work related to the following potential construction work packages. (Additional work packages may be identified during the preconstruction period.) – Limited Site Preparation – Portal Removal and Replacement – Tunnel Rehabilitation of Tunnel 1 at 2,699 feet and Tunnel 2 at 2,029 feet.

Location: Goshen Irrigation District, NE