Facility One Pump Station And Force Main Improvements

Facility One Pump Station and Force Main Improvements

Location: Ohio

Posted Date: March 27, 2024

Posted Date: March 14, 2024

Expiration Date: April 10, 2024

State: OH

Description: The work consists of the following: installation of approximately 1732 feet of 6” force main, 42 feet of 14” steel encasement pipe (bored), 1 air release manhole, 1 force main valve vault, 1 manhole, 40 feet of 6” gravity sewer, 40 feet of 8” gravity sewer, 37 feet of 12” gravity sewer, and related valves and fittings; installing a new sanitary pump station; taking the existing pump station dry well out of service; converting the existing pump station wet well to a sanitary manhole; abandoning approximately 2,941 feet of ex. 10” force main; electrical improvements; and related restoration and erosion control items.

Location: Toledo-Lucas County, OH

Estimated Cost: $1,100.000