Stiver Engineering provided liner plate tunnel and bore pit design (launch and receiving) for 10 tunnel crossings as part of this integrated pipeline project. We also provided a trench safety design for pipeline installation, calculations for required jacking loads for carrier pipe in tunnels, and a grouting plan that accounted for pipe buoyancy calculations. This $21 million project for the Tarrant Regional Water District included 2,000 linear feet of 9-foot, 5-inch excavated diameter tunnel in 10 different tunnels crossing Texas Department of Transportation roads, each with launch and receiving shafts (20 shafts).